Job Order
Create the job order after design approval and quotation confirmation📋Job Order Details
JOB-2026-00012
08 Oct 2026
Al Madeena Store
QTN-2026-01297
Brown Paper Bag with Handle
5,000 pcs
35 × 25 × 12 cm
2 colours (Front & Back)
Kraft Paper 90 gsm
Twisted Handle
15 Oct 2026
Normal
Status
Released
📦Product Preview


⚙Specification & Instructions
| Material | Kraft Paper 90 gsm (Brown) |
| Size | 35 × 25 × 12 cm |
| Handle Type | Twisted Handle (Brown) |
| Printing | 2 colours (Front & Back) |
| Finishing | Cutting, Folding, Pasting, Handle Fixing |
| Special Instructions | Use approved artwork v2. Maintain colour accuracy. Pack 100 pcs per carton. |
| Artwork File | PDFDSN-2026-00031_v2.pdf ⬇ |
| Approved By | Store Manager, Al Madeena (customer) |
| Approval Date | 07 Oct 2026 |
📦Material Requirement
| Material | Specification | Required Qty | Unit | Rate (QAR) | Amount (QAR) |
|---|---|---|---|---|---|
| Kraft Paper | 90 gsm (Brown) | 150 | kg | 6.00 | 900.00 |
| Handle | Twisted (Brown) | 5,000 | pcs | 0.15 | 750.00 |
| Glue | PVA Glue | 5 | kg | 4.00 | 20.00 |
| Ink | Flexo Ink (2 colours) | 2 | kg | 40.00 | 80.00 |
| Total Material Cost | QAR 1,750.00 | ||||
🔍 Store checks stock next
(step 5) — issued on Stock Release SRF-2026-00014.
⚙Resource Plan
| Resource | Planned | Rate (QAR) | Amount (QAR) |
|---|---|---|---|
| Printing Machine | 8 hours | 40.00 | 320.00 |
| Finishing Machine | 4 hours | 40.00 | 160.00 |
| Labour (2 operators) | 24 hours | 25.00 | 600.00 |
| Total Machine & Labour | QAR 1,080.00 | ||
| Wastage Allowance | 2% (100 pcs) | - | |
| Planned Output | 5,100 pcs | - | |
| Expected Good Qty | 5,000 pcs | - | |
🧮Job Cost Summary
| Material Cost | QAR 1,750.00 |
| Labour Cost | QAR 600.00 |
| Machine Cost | QAR 480.00 |
| Other Cost (packing, overhead) | QAR 270.00 |
| Total Job Cost | QAR 3,100.00 |
| Selling Price (from quotation) | QAR 4,000.00 |
| Expected Profit | QAR 900.00 |
| Profit Margin | 22.5% |
📅Job Schedule
| Process | Start | End | Duration | Assigned To | Status |
|---|---|---|---|---|---|
| Material Preparation | 08 Oct 2026 | 08 Oct 2026 | 0.5 day | Store · MD Shamim | Scheduled |
| Printing | 09 Oct 2026 | 09 Oct 2026 | 1 day | Printing · Parsad | Scheduled |
| Finishing (Cut, Fold, Paste, Handle) | 10 Oct 2026 | 10 Oct 2026 | 0.5 day | Finishing · Caleb, Yakub | Scheduled |
| Quality Check | 10 Oct 2026 | 10 Oct 2026 | 2 hours | QC · Ramadhan | Scheduled |
| Packing (100 pcs / carton) | 11 Oct 2026 | 11 Oct 2026 | 0.5 day | Paper Bag Section | Scheduled |
| Delivery | 15 Oct 2026 | 15 Oct 2026 | same day | Driver · Faizal | Scheduled |
| Total on the floor | ≈ 3 days | ready 11 Oct · delivery 15 Oct | |||
👥Team Assignment
| Name | Role | Shift |
|---|---|---|
| Rafeeq (ST008) | Production Manager | Day |
| Ramadhan (ST024) | Supervisor / QC | Day |
| Parsad | Printing Operator | Day |
| Caleb | Finishing Operator | Day |
| Yakub | Pasting & Handle | Day |
| MD Shamim (ST058) | Store Keeper | Day |
📝Notes
Use only approved artwork v2.
Check colour accuracy before mass production.
Maintain quality and follow the delivery schedule.
Check colour accuracy before mass production.
Maintain quality and follow the delivery schedule.
Worked example for Al Madeena Store · same job as
step 1, step 2 and
step 3 · buttons open the real screens (login needed) ·
← back to the full job journey