4

Job Order

Create the job order after design approval and quotation confirmation

📋Job Order Details

JOB-2026-00012 08 Oct 2026 Al Madeena Store QTN-2026-01297 Brown Paper Bag with Handle 5,000 pcs 35 × 25 × 12 cm 2 colours (Front & Back) Kraft Paper 90 gsm Twisted Handle 15 Oct 2026 Normal Status Released

📦Product Preview

Brown paper bag with handle
Front SideBack

⚙Specification & Instructions

MaterialKraft Paper 90 gsm (Brown)
Size35 × 25 × 12 cm
Handle TypeTwisted Handle (Brown)
Printing2 colours (Front & Back)
FinishingCutting, Folding, Pasting, Handle Fixing
Special InstructionsUse approved artwork v2. Maintain colour accuracy. Pack 100 pcs per carton.
Artwork FilePDFDSN-2026-00031_v2.pdf ⬇
Approved ByStore Manager, Al Madeena (customer)
Approval Date07 Oct 2026

📦Material Requirement

MaterialSpecificationRequired QtyUnit Rate (QAR)Amount (QAR)
Kraft Paper90 gsm (Brown)150kg6.00900.00
HandleTwisted (Brown)5,000pcs0.15750.00
GluePVA Glue5kg4.0020.00
InkFlexo Ink (2 colours)2kg40.0080.00
Total Material CostQAR 1,750.00
🔍 Store checks stock next (step 5) — issued on Stock Release SRF-2026-00014.

⚙Resource Plan

ResourcePlannedRate (QAR)Amount (QAR)
Printing Machine8 hours40.00320.00
Finishing Machine4 hours40.00160.00
Labour (2 operators)24 hours25.00600.00
Total Machine & LabourQAR 1,080.00
Wastage Allowance2% (100 pcs)-
Planned Output5,100 pcs-
Expected Good Qty5,000 pcs-

🧮Job Cost Summary

Material CostQAR 1,750.00
Labour CostQAR 600.00
Machine CostQAR 480.00
Other Cost (packing, overhead)QAR 270.00
Total Job CostQAR 3,100.00
Selling Price (from quotation)QAR 4,000.00
Expected ProfitQAR 900.00
Profit Margin22.5%

📅Job Schedule

ProcessStartEndDurationAssigned ToStatus
Material Preparation08 Oct 202608 Oct 20260.5 dayStore · MD ShamimScheduled
Printing09 Oct 202609 Oct 20261 dayPrinting · ParsadScheduled
Finishing (Cut, Fold, Paste, Handle)10 Oct 202610 Oct 20260.5 dayFinishing · Caleb, YakubScheduled
Quality Check10 Oct 202610 Oct 20262 hoursQC · RamadhanScheduled
Packing (100 pcs / carton)11 Oct 202611 Oct 20260.5 dayPaper Bag SectionScheduled
Delivery15 Oct 202615 Oct 2026same dayDriver · FaizalScheduled
Total on the floor≈ 3 daysready 11 Oct · delivery 15 Oct

👥Team Assignment

NameRoleShift
Rafeeq (ST008)Production ManagerDay
Ramadhan (ST024)Supervisor / QCDay
ParsadPrinting OperatorDay
CalebFinishing OperatorDay
YakubPasting & HandleDay
MD Shamim (ST058)Store KeeperDay

📝Notes

Use only approved artwork v2.
Check colour accuracy before mass production.
Maintain quality and follow the delivery schedule.
Worked example for Al Madeena Store · same job as step 1, step 2 and step 3 · buttons open the real screens (login needed) · ← back to the full job journey